Cheniere seeks FERC OK to build two more Corpus Christi LNG trains

US LNG exporting giant Cheniere has filed an application with the US FERC seeking authorization to construct two midscale trains at its Corpus Christi LNG export plant in Texas.

The Corpus Christi liquefaction plant now consists of three operational trains with each having a capacity of about 5 mtpa.

In June last year, Cheniere took a final investment decision on Stage 3 expansion and officially started construction in October.

Under the expansion, Cheniere will add up to seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa, with a total production capacity of more than 10 mtpa.

Besides this expansion, Cheniere plans to build two more liquefaction trains and one storage tank as part of the third expansion phase at the plant.

Cheniere detailed the plan for the proposed Corpus Christi Liquefaction Midscale Trains 8 & 9 Project in August last year.

Majority of volumes committed

Cheniere’s units filed a formal application to build these two trains on March 30, according to a filing with FERC.

The company is asking FERC to grant this application by September 27, 2024.

Cheniere seeks FERC OK to build two more Corpus Christi LNG trains
Image: Cheniere

According to Cheniere, the project would include two trains, nearly identical in design to trains 1-7 and each capable of producing up to 1.64 mtpa of LNG, on-site refrigerant storage, a 220,000-cbm LNG storage tank, a BOG compressor, and an increase in the authorized LNG loading rate.

The project would result in an increase in the maximum marine vessel traffic from the 400
LNG carriers per year authorized at the terminal, up to 480 LNG carriers per year.

Cheniere said it would supply feed gas to the project via a combination of the previously permitted Corpus Christi Pipeline facilities and the ADCC pipeline, a non-jurisdictional intrastate pipeline designed to transport up to 1.7 Bcf/d, to be operated by WWM Operating.

Moreover, commercialization of the project “is substantially complete, with a majority of LNG export volumes from the project facilities committed via long-term LNG sales contracts,” Cheniere said.

The firm is seeking the approval from FERC by September 27, 2024 so that it may commence construction of the project in the second half of 2024.

If constructed under optimal conditions, Cheniere expects the construction to last four years.

“However, applicants are seeking authorization to complete construction and place the facilities in service by 2031 to accommodate the potential for phasing, schedule changes or other unforeseen disruptions,” it said.

Most Popular

Venture Global’s Plaquemines LNG to commission third jetty

US LNG exporter Venture Global LNG has received approval from the US FERC to introduce hazardous fluids to the third jetty at its Plaquemines LNG export plant in Louisiana.

Samsung Heavy, KR to develop three-tank LNG carrier

South Korean shipbuilder Samsung Heavy Industries signed a memorandum of understanding with compatriot classification society KR to jointly develop a 174,000-cbm LNG carrier featuring three cargo tanks.

Another FSRU arrives in Egypt

The 160,000-cbm FSRU Energos Eskimo has arrived in Egypt from Jordan, according to shipping data. The unit is one of four FSRUs that will serve a charter deal with Egypt's EGAS as the country seeks to meet its growing demand for natural gas.

More News Like This

Cheniere’s Corpus Christi expansion project almost 84 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is almost 84 percent complete.

Venture Global’s Plaquemines LNG to commission third jetty

US LNG exporter Venture Global LNG has received approval from the US FERC to introduce hazardous fluids to the third jetty at its Plaquemines LNG export plant in Louisiana.

Port of Corpus Christi completes ship channel expansion

The US Port of Corpus Christi in Texas has completed the $625 million ship channel improvement project.

Cheniere kicks off Sabine Pass LNG maintenance

US LNG exporting giant Cheniere has started planned maintenance at its Sabine Pass LNG export facility in Louisiana.
OSZAR »